Several project management models include provisions to manage risk. Risk is here defined as a probability for an adverse event times the quantified consequence of that adverse event. The IBM Rational Unified Process recommends addressing risk while planning the iterations of what in RUP is called Elaboration phase. Barry Boehm’s Spiral Model is guided by risk considerations. So are the various versions of the Stage-Gate model. The Scrum literature, while mentioning risk as one of the prioritization principles for the product backlog, leaves it mostly to the judgment of the product owner to make a good prioritization.

We can intuitively understand that creating something entirely novel such as a car that runs 10 000 km without refueling is more risky than developing next year’s model of an existing car with only some cosmetic changes. The risk in new product development is usually not evenly distributed on all tasks in the development project. Developing the engine of the ultra-long-range car (ULRC) carries far more risk than developing the entertainment system or the suspension.

Risk-driven development means that we want to eliminate as much risk as we can, as fast as possible, in any way possible; we don’t want to end up having invested a large amount of money and reputation in a project that after all that investment still has a high probability of failure. We also have to take into account the opportunity cost, the gain we would have got if we had invested the money in another project.

As an illustration, assume that the biggest uncertainty in a project (like the ULRC engine) is left as the last component to be developed in the project, then we would end up having invested a lot of money in the project without still knowing if the product will ever work. The cost of the risk being realized would be the opportunity cost plus the total accrued project cost up to the time of the ultimate failure.

We can also look at it from an capital budgeting point of view. When selecting investment targets, we always wish to match return and risk. For a particular level of risk we expect a certain level of (expected) return. Assuming that the income from the project is fixed (as long as it succeeds), then the risk level at which we invest our next unit of money in the project should be guiding our willingness to make that investment; the lower the risk, the more attractive the investment. I will try to elaborate on this in later posts.

When developing an ULRC it is probably thus not be wise to start with specifying and designing the entertainment system or the suspension. Neither does a comprehensive and approved requirements specification help much to lower the risk in this particular case. The only novel requirements may be the 10 000 km range and that’s easy enough to understand and to write down. Instead we should, as already hinted above, focus on designing and building prototypes of the long-range engine and its related parts.

There are of course variations to the risk-driven development theme. In some cases we need to build some low-risk parts first to be able to even start with the high-risk parts. For instance, we may need to build the rest of the powertrain or at least a test bench simulating the rest of the powertrain to be able to carry out tests with the new engine.

One framework for risk-driven development is, as mentioned in the introduction, the Stage-Gate process consisting of phases (stages) and tollgates. The tollgates are decision points at which the future execution of the project is decided based on the project’s risk level so far. If we at a certain tollgate think the risk is too high for a substantial new investment, e.g. for ramping up development or starting an expensive marketing campaign, then we need to find ways to lower the risk further before we make the additional investment. If we can’t find such ways, then we may need to abort the project altogether.

A problem with the Stage-Gate model is that it is often confused with a waterfall development model which e.g., mandates that the product requirements are developed and preferably frozen and approved in the beginning of the project. Indeed, in many quality management systems the tollgate criteria are defined in terms of produced documents and those criteria are the same for all projects.

The Scrum process doesn’t have formal tollgates. All development in Scrum is made in sprints (similar to iterations). The progress of the project is checked after each sprint and adjustments are made to both the plan and the process as needed. Scrum does not mandate any particular order in which the product should be developed but recommends that potentially shippable product increments are delivered as a result of each sprint. (This usually works for software but maybe not for a car.)

To conclude, here are a couple of ideas that should make the Scrum and the Stage-Gate processes more effective together:

  • Rename the risk list that exists in most project models to risk backlog and think of it in the same way as about the product backlog in Scrum. This implies an order in which the risks shall be addressed and should be used to plan the project (iterations, sprints, whatever). Risk-driven activities include developing functionality, interviewing customers, building prototypes, doing analyses, and so on.
  • Use the risk backlog as the main input to the tollgate decisions criteria in the Stage-Gate model. The tollgate criteria should be allowed to vary from project to project and should be concerned about the biggest remaining risks in the project (including risks such as that there is no market for the product we are developing). The fixed lists of documents that is often used as tollgate criteria do not fit every project since they do not match the risk profile of every project. It is after all risk that we wish to assess at the tollgate and the risk backlog, including any more detailed material on each risk, is the main indicator of project risk.
  • Synchronize any gate decision with the end of a sprint and make sure that whatever is required for the gate decision is produced in the last sprint(s).